€25m Mayo University Hospital expansion moves into construction phase


New Emergency Department and Acute Medical Assessment Unit will provide 45 treatment and examination spaces and dedicated paediatric facilities
Construction is now underway on the major €25 million expansion at Mayo University Hospital, with contractors onsite delivering a new Emergency Department and Acute Medical Assessment Unit.
The three-storey development will provide 45 treatment and examination spaces, four resuscitation rooms and a dedicated paediatric emergency department.
The project is designed to provide additional space, improve patient flow and allow for faster assessment, while also providing safer and more private care for patients and families.
Mayo Minister Alan Dillon welcomed the progress, saying he had first raised the need for an expansion of the hospital’s emergency facilities in the Dáil in 2020.
“Having first raised the need for this expansion in the Dáil in 2020, it’s great to see this large scale capital project moving from plans to delivery,” he said.
The HSE confirmed earlier this year that the project was progressing, with its Board approving the contract award for the extension of the Emergency Department, including an Acute Medical Assessment Unit.
A contract award notice for construction of the Emergency Department extension and Medical Admissions Unit was subsequently published in August 2026.
The current timeline envisages construction taking place during 2026, with the new Emergency Department and Acute Medical Assessment Unit scheduled for completion in the second or third quarter of 2028.
An ambulance set-down area is expected to be completed in the third quarter of 2028, followed by refurbishment of the existing Emergency Department, which is scheduled for completion in the fourth quarter of 2029.
The development will allow the existing Emergency Department to remain operational while the new facilities are delivered before the final refurbishment works take place.
The project has been in development for several years, with planning permission for the Emergency Department and Acute Medical Assessment Unit granted in March 2024. HSE documentation at the time outlined plans for a new extension and reconfiguration of the existing Emergency Department alongside a new Medical Assessment Unit.
Minister Dillon said the investment represented a significant step forward for patients, families and staff across Mayo.
He also said he would continue to engage with the HSE to ensure the project remains on schedule.
The HSE has previously said the expansion will increase clinical capacity, improve patient flow and provide enhanced treatment and assessment areas to meet current and future demand at Mayo University Hospital.