MacHale Park pitch not perfect
Mayo GAA chief says surface 'must be minded'
MAYO GAA chairman Seamus Tuohy says that the pitch at Hastings Insurance MacHale Park in Castlebar will ‘have to be managed carefully’ for the rest of this year with only a limited number of games expected to be played there.
Speaking to The Mayo News, Tuohy explained that a combination of ‘over-use and bad weather’ in the last 12 months meant that grass roots growth had been impacted.
As a result, only the Mayo senior football championship final looks set to be played there next October with most (if not all) of the other adult finals set to be fixed for other venues.
“It’s not about closing MacHale Park, it’s about giving the pitch there the opportunity for root growth,” he said.
“There’s a need to curtail the number of matches being played there in order to give the grass roots the opportunity to develop. We didn’t get the opportunity to do that in 2022.
“It takes a pitch about two years to get to the level of maturity to allow the roots to develop, and the weather is a big factor.
“The county senior final will be played there, but I can’t see double-headers being played there,” he added. “Last year we had two club matches on Saturdays and two on Sundays.
“I can’t see that sort of scenario happening this year.
“For example, the County Junior ‘B’ and Junior ‘A’ Finals are down for Saturday, October 28 and the County Intermediate and Senior Finals are down for Sunday, October 29. .
“I can’t see them being played as double-headers in MacHale Park.”
Work was carried out on the pitch at MacHale Park between August 2021 and April 2022, with the installation of a new and improved drainage system, a lengthening of the pitch by five metres and a complete reseeding of the playing surface.
The work — which is estimated to have cost in the region of €300,000 — was completed in time for the Connacht SFC match between Mayo and Galway 13 months ago.
However, Seamus Tuohy told a County Board last November that Mayo GAA chiefs were ‘not happy’ about a number of issues that arose with the pitch last Autumn, and concerns have also been expressed by club delegates at subsequent board meetings.
The Mayo News understands that the pitch was closed to all activity — including Mayo senior and minor squad training — last week.
Both teams are expected to train there this week, with Mayo also at home to Louth at MacHale Park next Sunday afternoon.
Tuohy admitted that the pitch was ‘over-used’ in the last 12 months.
“We need to manage that better, we need to manage the pitch carefully.
“We seeded our pitch in September 2021 and re-opened it in April 2022, so there was a six-month period there. . In the normal run of things, there would have been more time between a pitch being seeded and re-opened.
“But we didn’t have much option at the time. . The pitch was good, it took that game between Mayo and Galway well, so I wouldn’t pin-point that game as being an issue.
“But if you put two or three games into it in a short period of time, and then the weather starts to become a problem, that’s when problems arise.
“Our supporters have invested heavily in the pitch, and I’d hope that in 12 months’ time that we’d be able to host all games. It has to be managed, any pitch has to be minded.
“A lot of work has been done, and is being done, for the Louth game in terms of sanding and draining. It needs attention. I’d hope it would be at its best for next Sunday,” he concluded.