Mayo councillors advised against making changes to Ballina Flood Scheme


Ballina councillors told that making changes to the Ballina Flood Relief Scheme may trigger new planning process and delay the scheme
North Mayo councillors were advised that trying to introduce changes to the Ballina Flood Relief Scheme may lead to delays in the construction of the scheme.
A presentation on the €55 million Ballina Flood Relief Scheme was presented to members of the Ballina Municipal District this morning where they were informed that the construction stage is due to begin in August 2027 and will take four and a half years to complete.
During the presentation, Mayo County Council engineer, Michael O'Grady explained that the scheme is currently in the design stage and that a mock flood wall along Bachelors Walk illustrates what it would look like.
While welcoming the scheme, Fine Gael councillor Marie Therese Duffy said she received numerous queries and concerns from members of the public regarding the height of the mock flood wall preventing people from seeing the River Moy.
“I don't know the exact height of the wall, but I cannot actually see the river anymore at that mock up section. So I'm just wondering if there's any way that that could be lowered because when you are in the town centre, you want to be able to see the river,” she said.
Cllr Duffy also asked the council to reconsider the use of stainless steel railings on Cathedral Road and instead reinstate the traditional black steel railing currently along the river 'in keeping with the historic character of Ballina town'.
Mr O'Grady replied that lowering the height of the wall would 'defeat the whole purpose of the scheme' and defended the use of stainless steel railings. He added that there isn't an opportunity for making changes 'because it's gone through planning, and that's what's been approved'.
Director of Services, Catherine McConnell also pointed out that because planning permission has been granted for the scheme, changes cannot be made and doing so will delay the commencement of the construction phase.
“While I take your point, I think to start changing details now at that stage would possibly trigger a Part 8 [planning process] and at this stage I really don't want to be doing that,” she said.
In October 2025, Coimisiún Pleanála granted planning permission for the Ballina Flood Relief Scheme along the River Moy and its tributaries which is designed to provide flood protection to 187 homes and 54 businesses in the north Mayo town.
The scheme design for Ballina consists of the construction of flood defence walls, construction of embankments and culvert upgrades along the River Moy and the following tributaries, Quignamanger, Bunree, Brusna, Tullyegan and Knockanelo.


These works will include the construction of new quay walls, repairs/rebuilding of existing quay walls and the creation of a new raised plaza along Cathedral Road and the construction of four new (sub-surface) pumping stations and a new stormwater collection network along the River Moy quays.
The councillors were told that Ballina was very lucky to have the scheme commissioned and receive planning 'in record time' as there were other towns around Ireland which suffer from flooding which are still waiting for a scheme to be commissioned.
Mr O'Grady also explained that the proposed wall at Bachelors's Walk is 1.5m in height and will be the highest part of the scheme and there is no change to the height of the walls currently in place at other locations.
“Bachelor's Walk is significantly more at risk for tidal flooding, which is a lot more unpredictable than alluvial or river flooding. So, to lower it you would run the risk of obviously having those people flooded. It would actually invalidate the scheme anyhow, and it would not be funded,” he said.
In relation to the railing along Cathedral Road, he said that discussions were had with conservation architects and it was their view that the current railings ‘don't have much of a heritage value as people may think’.
While thanking the officials for their answers, Cllr Duffy reiterated her opinion that the heritage of the town should be protected in the scheme.
“I know there is a push nowadays with modern but I would just reiterate again that the traditional look and heritage of the town and the historic centre should be preserved if at all possible. Is there any way at all possible that that could be looked at again?” she said.
Mr O'Grady defended the conservation process during the scheme saying that they are recovering the original stone and using it on Bachelor's Walk even though it is increasing the cost of the scheme.
“I understand what you're saying and people might agree or disagree with you and I think in this case we can certainly mention it. But my view would be that it is probably something we can't change.
“We don't want to trigger something that will take you back to any kind of planning or appropriate assessment. We kind of are where we are and we're going forward rather than back,” he said.