Mayo engineers to keep flood scheme traffic disruptions to a minimum


Mayo council engineers say that only one street in Ballina will be closed to traffic to facilitate the Ballina Flood Relief Scheme works
Mayo council engineers say they will try to minimise traffic disruption during the construction of the Ballina Flood Relief Scheme but one street will be closed to traffic.
The construction of the €55 million Ballina Flood Relief Scheme is scheduled to begin in August 2027 and is estimated to take four and a half years to complete.
A presentation on the scheme was given to members of the Ballina Municipal District at its monthly meeting in Ballina with new flood defense walls proposed along the River Moy for Ridgepool Road, Bachelor's Walk and Clare Street while it is also proposed to develop a raised plaza and public realm space for Cathedral Road.
Michael O'Grady, engineer with Mayo County Council said in addition to these works, four pumping stations will be installed at Ridgepool Road, Bachelor's Walk, Clare Street and Barrett Street.
The scheme along the River Moy and its tributaries is designed to provide flood protection to around 300 homes with the bulk of the work to take place along the Moy.
Mr O'Grady said to minimise disruption to the angling in the Moy, work will begin at the Ridgepool in early August 2027 and timelines for other areas of the river will be confirmed in the new year.
He said that there will be traffic disruptions during the construction of the scheme and parking spaces will be taken from these streets. He stressed that apart from Barrett Street which will be closed for a few days to cater for the installation of a pumping station, they have ensured that there will be no other road closures.
“We have looked at the construction methodology that we are going to use and we have concluded that we will be able to maintain a two way traffic system along Clare Street and Howley Terrace. The trade off is we will have to remove the parking along the east side of Clare Street and we will facilitate those who use the on-street car parking at an alternative parking space.
“The one area that probably will be difficult would be Barrett Street where an underground pumping station will be constructed there. The ancillary works will probably be done in the evening but the actual installation of the underground pumping station there will most likely necessitate the closure of that road for a few days,” he said.
The councillors were also informed that streets may need to be dug up to deal with sewerage and water services and that telecom lines which are currently overground will be put underground.
Mr O'Grady was also asked how the scheme will affect car parking when it is completed and if the car parking spaces which will be taken away will be reinstated.
He replied that the car park spaces taken away during construction will be reinstated but stressed that increasing or decreasing over car parking spaces will have to be addressed by the municipal district after it is completed.
Cllr John O'Hara said that the Church who are the owners of a car-park at the Cathedral Road are happy to make it available during the term of the construction and asked officials to make contact with them.
The current state of the surface of Cathedral Road was raised by Cllr Marie Therese Duffy who asked when it be resurfaced. Mr O'Grady said that the timeline for working on Cathedral Road is not yet known but did not expect work to begin on it for another two to three years.
He advised against resurfacing it until all the scheme is completed but stressed it is a structurally a good street which will not deteriorate.
“There is no point in resurfacing the street and us coming back and digging it up because that makes absolutely no sense to anybody,” he said.