WORK on a €800,000 extension to Breaffy NS ceased after the Westport building contractor went into liquidation

WORK stopped on the construction of an €800,000 extension to Breaffy National School outside Castlebar last week after the building contractor went into liquidation, another sign of the downturn in the building industry.

Workers left the site on Wednesday when news came through that Westport company Keegan Construction had gone into liquidation, leading to uncertainty over the completion of the extension, which comprises of six classrooms.

On behalf of the Board of Management of the school, Breaffy NS principal George Moran said the events were ‘unfortunate’ and was keen to praise the builder, Tony Keegan, and his staff and sub-contractors.

“From the board’s dealings with Mr Keegan and the sub-contractors it was always evident that Mr Keegan was held in the highest esteem by all involved in the school building project. We are not going to be inconvenienced too much by the delay. The foreman John Cusack and the staff were lovely to work with at all times and very thorough in their work. Mr Keegan is highly reputable and any architects or engineers I’ve met who have dealt with him always said that.”

The project was due to be completed this September but temporary accommodation in the nearby community centre will continue to be used. A liquidator has been appointed and is due to speak with George Moran today (Tuesday).

It is believed that workers on the project were largely paid up to date for their labour and George Moran is hopeful that Keegan Construction will be allowed complete the project after the liquidator carries out his/her work.

“There is still a possibility that the project will be finished by Keegan Construction and that would be a favourable outcome.”

Were that not to happen, problems would present themselves as any new developer would not be in a position to guarantee the work carried out to date, unless the site was fully assessed.

All will become clear in the coming weeks.