National problems seriously impacting local projects in Mayo

The worsening situation in the public finances is stalling capital projects in Mayo, and those for which contracts are not signed or on which work is not under way may never be started.

National problems seriously impacting local projects in Mayo

Neill O’Neill

THE worsening situation in the public finances is stalling capital projects in Mayo, and those for which contracts are not signed or on which work is not under way may never be started.

That was the warning from one of Mayo County Council’s senior figures at a meeting of the Council’s Water Supply and Sewerage Strategic Policy Committee last week, where an update was given on the water services investment programme 2007-2009.

Mayo County Council is currently owed over €7 million by the Department of the Environment and will not be proceeding with any capital investment projects until it receives more of this money.

Countywide, there are plans for over €205 million of investment in water and sewerage, but realistically, very little of this work will begin this year. Senior Executive Engineer, Mr Joe Beirne, informed last week’s meeting that implications from the national budget will affect the Council’s plans and that 30 per cent of the price of the schemes has to be raised locally, ‘which is not easy to do’.

“If we get the projects we have at tender to construction this year we will be doing good,” he said. “If we get anything to tender in the next few years will be up to the national situation and our own ability to meet our requirements under the polluter pays principle.”

The contractor for the Achill Sewerage Scheme – which has since been approved – is still willing to go ahead with the work for the price agreed on, however, in Kiltimagh, the contractor has indicated that he may withdraw from the sewerage project.

The proposed sludge hub centre at Derrinumera has been refused, as it is currently planned, by An Bord Pleanála, which is also holding up plans for a sewerage scheme for nearby Newport.

The Srah to Westport water extension and treatment plant at Tourmakeady has been delayed by the absence of a €6.6 million polluter pays contribution, while no local contribution has been raised for the planned Westport to Louisburgh water mains extension. Mayo County Council were due to discuss the possibility of obtaining a loan for €8.8 million for these schemes yesterday (Monday), which if approved could get them moving.

In Belmullet, the requirement to obtain a foreshore licence has delayed a planned sewerage scheme for the town, and the North Western Fisheries Board have also opposed the plan, saying that the scheme will negatively impact on oyster beds in the area. The Council disagrees with this and the Environmental Protection Agency are due to make a decision on it in coming weeks.

Joe Beirne informed the meeting that getting money from the Department can be a long and drawn-out process.

“We will be lucky to get the bill down to €5 million and it has never been at zero in my 20 years here,” he said. “ If the Department release more money then we can start more projects but it is hard to get the money and hard to borrow these days. It is a problem that is exasperated by the requirement to find 30 per cent of the costs, and the only way to do this is through betterment charges and water levies.”