Electricity upgrade for Westport

No energy crisis in McAllister’s Green gaitplaceholder image
No energy crisis in McAllister’s Green gait

CONSTRUCTION of the 110kv electricity line between Westport and Castlebar is due to start by the end of June next.

CONSTRUCTION of the 110kv electricity line between Westport and Castlebar is due to start by the end of June next.

The project, which involves a €27 million investment by the ESB, encompasses 22 kilometres of overhead lines between the two towns and will entail the erection of a new station at Carrowbeg, Westport.

Company representative, Ms Mary Keogh made a presentation to councillors at last week’s meeting of Westport Town Council. She detailed how the upgrade will improve the quality of supply for Mayo, thus providing a good infrastructure for potential investors.

She  revealed that 79 landowners will be affected along the route, with talks ongoing since February last.

Ms Keogh also said that an announcement on the contractor is expected in the coming days.  It is projected the overhead line will be completed by March 2010.

 The station at Carrowbeg also has a start date by the end of June and will take six months to complete, while work on a station for Castebar is due to begin during September next.

She added that the full project is due to be completed by September 2010.

 Town Manager Mr Peter Hynes (pictured) remarked that this is probably one of the most important infrastructural projects in the Westport area since the sewerage scheme.

 “Until now the electricity situation has been to some extent quite precarious. This €27 million investment will secure Westport’s supply situation and make the town a viable location for industrial development,” said Mr Hynes.