The chairman of An Bord Pleanála’s hearing into the modified pipeline route for the Corrib gas project has asked Mayo County Council to provide him with a report on key infrastructural developments.

THE chairman of An Bord Pleanála’s hearing into the modified pipeline route for the Corrib gas project has asked Mayo County Council to provide him with a report on key infrastructural developments being proposed for north-west Mayo. 

Under the remit of a development forum,  established last November by two government ministers, Éamon Ó Cuív and Eamon Ryan, this report will identify key strategic infrastructural developments for the area, the hearing was advised.

Mr Ian Douglas, a senior county council planner, said he understood the report would be ready soon.

At yesterday’s hearing in Belmullet, the negative impact of the project on the Glenamoy bog complex (SAC) – as elucidated upon in a  Department of Environment submission – was strongly challenged by counsel for Shell, Mr Esmonde Keane.  

Earlier, speaking for the county council, Mr Douglas also said that the modified pipeline will have ‘a negligible impact on the landscape’, on drinking water schemes and on designated conservation sites. He observed that mitigation measures will be undertaken at the landfall site and along the route of the pipeline after its construction.

The chairman, Mr Martin Nolan, asked him to identify what body had primary responsibility for safety of the pipeline, its related regulatory regime and if the council intended retaining experts to monitor the implementation of this safety system.

Mr Nolan also observed that he wanted to establish what role Mayo County Council and the Fire Services would play in its implementation.

 Responding, Mr Seamus Murphy, the Chief Fire Officer, said ‘the matter of the safety of the pipeline was for the Department of Energy’.

He also explained that his involvement with the project would not be until after it has approval.

“If the project gets approval, we will draw up a site-specific plan for an emergency response – like, for example, we have done for Knock Airport,” said Mr Murphy.

Meanwhile, the chairman interjected when Mr Peter Sweetman, an environmental consultant, raised a question about An Bord Pleanála’s jurisdiction over a section of the pipeline route, at the Glengad landfall site, where Shell is working presently.

“I have sought further information this morning regarding the footprint of the gas pipeline,” said Mr Nolan. He added that he needed to examine what arrangements had been made between Shell and Mayo County Council about these works.

Referring to the ‘temporary works’ at Glengad, Mr Sweetman also asked Ian Douglas had he recently inspected the Shell compound at Rossport. He responded that he had not done so recently but that it was not restored when he last inspected it.

“Your idea of ‘temporary’ goes on forever,” said Mr Sweetman.

In a submission by the Department of the Environment, Ms Caitriona Douglas said that insufficient evidence had been provided in the EIS Addendum by the developer.

She referred specifically to the impact of the construction of a stone road on ‘the mosaic’ of bog pools which are ‘highly sensitive’ to surface and sub-surface groundwater.

Counsel for Shell, Esmonde Keane challenged the extent of the impact.

The hearing continues today (Tuesday).