Ballinrobe gas put ’on hold’
HAVING worked so diligently to secure a gas connection for Ballinrobe after initial projections from Bord Gáis had denied the town a connection, the business people of Ballinrobe now face the prospect yet again of an indefinite wait for gas to be connected to the town.
Ballinrobe gas put ‘on hold’
Michael Duffy
HAVING worked so diligently to secure a gas connection for Ballinrobe after initial projections from Bord Gáis had denied the town a connection, the business people of Ballinrobe now face the prospect yet again of an indefinite wait for gas to be connected to the town.
Mr Fiachra Quigley of Bord Gáis Networks informed councillors at yesterday’s (Monday’s)Ballinrobe Electoral Area Committee that their plans to bring natural gas to Ballinrobe are ‘on hold due to lower than expected demand from local industry’.
“Bord Gáis Networks (BGN) is active in Ballinrobe and continues to engage with the business community and potential commercial customers and developers in the town. Some businesses have expressed interest in connecting to natural gas and are currently assessing the quotations received. Discussions are ongoing with the remainder of the business community regarding their commitments to utilise natural gas. Subject to securing the projected level of demand, BGN will develop the construction plans to bring natural gas to the town,” said Mr Quigley at Monday’s meeting. He went on to explain that in November 2007, following approval by the Commission for Energy Regulation (GER) of the Bord Gáis Phase 2 study into the viability of new towns, Bord Gáis confirmed that, subject to achieving commitments that meet the level of demand required, Ballinrobe would be connected to the natural gas network. However, to date, commitments are below the required level.
“Despite this, Bord Gáis will continue to liaise with local businesses to ensure that natural gas will be available in Ballinrobe. BGN has committed to keeping the Electoral Area Committee informed throughout the project and is happy to meet with councillors again when there are further developments to report on,” said Mr Quigley.
Despite repeated attempts by Cllr Damien Ryan to ascertain how many more businesses would need to sign up before gas would be provided, Mr Mark Holohan, Sales Manager with BGN, said the discussions with businesses were ongoing and he was not at liberty to discuss commercial discussions.
“BGN is keen to see greater utilisation of its gas network throughout Mayo and Ireland and pursues growth opportunities, such as new towns like Ballinrobe, when they are viable. The key factors in determining viability are proximity to the natural gas network and the level of projected gas demand in the town. Connection of all new towns is subject to meeting the requirements for projected gas demand,” said Mr Holohan, who said it was not known when the projected volume of business would be reached in Ballinrobe.
Cllr Patsy O’Brien expressed concern that roadworks on roads surrounding Ballinrobe had been delayed as it was expected that works would be taking place on the roads due to the gas pipes being laid.
Mr Holohan said he would talk to local engineers to advance works, if the timing was suitable, as this had been done very successfully in Westport.
Mr Holohan went on to say that Bord Gáis were out there, giving people costs, but the reality was many businesses were now taking stock and seeing if it was commercially viable for them to install gas.
When pushed by Cllr Ryan, Mr Quigley said if everyone Bord Gáis had talked to had signed up they would be ‘over the line’, but given time, he was confident the figures would be reached.